Production | Production cycle | Materials | Technical process |
General mould | About 30 days |
|
|
Irregular mold(Common type) | 50 days |
|
|
Irregular mold(Special type) | 60~70 days |
|
|
|
Circular cutter | 15 days | DC53,SKD11,Cr12Mov | Digital controlled lathe,Internal and external circular grinding, Lower cutter is reversed |
Cutter plate | 15 days | 45#Steel plate | Bore a hole,Drill vent,Electroplating |
Common cavity | 10 days | Aluminium bar | Digital controlled lathe,Drill vent,Polishing |
Special process cavity | 20 days~25 days | Aluminium bar | Add to:Carving、Corrosion、Sand blasting, and so on |
Top head | 7 days | Copper, aluminum, Aluminum with hard oxygen | Digital controlled lathe,Carving,Drill vent,Polishing |
Stretch head | 5 days | Imported nylon rod, Sai Steel, Heidak | Digital controlled lathe,Polishing,Special-shaped needs to be carved |
Top shaft、Stretch shaft、Limit lever | 5 days | Hard chrome axis | Digital controlled lathe,Milling,Drill vent |